X

Henham Footbridge, Latitude Festival- Environmental

Client: Festival Republic (on behalf of Latitude Music Festival)

  • The brief was to replace the existing floating bridge with a permanent structure.
  • 12 helical piles designed to 8m were used.
  • The structure is 49m long by 12m wide.
  • The main structure was a steel frame and attached on top of the piles.
  • Installation took 21 days.