- Dudley’s Construction wanted a cost effective more efficient foundation solution compared to the traditional method and selected our superb pile system as the perfect
alternative. - 2 installers using 1 excavator completed the installation of 34 piles in just 5 days. There is no curing process so the modular building could be landed immediately onto the pile top-hats.